  The plan to build a sidewalk in Hyde Park Village is moving forward.  Members of the Hyde Park Village Enhancement Committee met with a VTrans project manager and engineers in Montpelier on August 19 to discuss the bidding process of the long awaited Depot Street sidewalk project. The project to build roughly 950 feet of sidewalk and improved handling of stormwater along Depot Street and Depot Street Extension in Hyde Park Village will be put out to bid on November 1 with construction to begin in April, 2013.  The sidewalk committee wishes to thank adjacent landowners and residents for their patience with this long process.   